Qualification standard of engineering supervision enterprise

time :2024-12-01 from: classify :Engineering supervision enterprise qualification

The qualification of engineering supervision enterprise can be divided into three sequences: comprehensive qualification, professional qualification and firm. The comprehensive qualification is only Grade A. In principle, professional qualification is divided into three levels: a, B and C, and according to the nature and technical characteristics of the project, it is divided into 14 professional engineering categories (schedule 2). Except for the four professional engineering categories of housing construction, water conservancy and hydropower, highway and municipal public works, there is no Class C qualification for other professional engineering categories. There is no hierarchy in the firm.


I. qualification standards


(1) Comprehensive qualification standards


1. It has the status of an independent legal person and the registered capital is not less than 6 million yuan.


2. The technical person in charge of the enterprise shall be a registered supervisory engineer with more than 15 years of experience in engineering construction or a senior engineering title.


3. Professional Grade A project supervision qualification with more than 5 engineering categories.


4. there are not less than 60 registered supervision engineers, no less than 5 registered cost engineers, and a total of not less than 15 registered architects, first-class registered structural engineers or other survey and design registered engineers.


5. The enterprise has a perfect organizational structure and quality management system, as well as a sound management system of technology and archives.


6. The enterprise has the necessary engineering test and testing equipment.


7. Within two years prior to the date of applying for the qualification of project supervision, the enterprise has not violated the laws, regulations and rules.


8. There are no major quality accidents caused by the supervision responsibility of the enterprise within two years prior to the date of applying for the qualification of project supervision.


9. In the two years prior to the date of applying for the qualification of project supervision, there were no major safety accidents of project construction at or above the third level or two or more than two safety accidents of the project construction of the fourth grade due to the supervision responsibility of the enterprise.


(2) Professional qualification standards


1. Class A


(1) having the status of an independent legal person and having a registered capital of not less than 3 million yuan.


(2) the technical person in charge of the enterprise shall be a registered supervisory engineer with more than 15 years of experience in engineering construction or a senior engineering title.


(3) the total number of registered supervision engineers, registered cost engineers, first-class registered builders, first-class registered architects, first-class registered structural engineers or other survey and design registered engineers shall not be less than 25; among them, the corresponding professional registered supervision engineers shall not be less than the number required in the Professional qualification registered Supervision Engineers (schedule 1), and the number of registered cost engineers shall not be less than 2.


(4) the enterprise has independently supervised more than 3 professional second-level engineering projects in the past 2 years, with the exception of those enterprises with Class A design qualification or first-class and above construction general contracting qualification to apply for Class A qualification of this professional engineering category.


(5) the enterprise has a perfect organizational structure and quality management system, as well as a sound technology, archives and other management system.


(6) the enterprise has the necessary engineering test and testing equipment.


(7) within two years prior to the date of applying for the qualification of project supervision, the enterprise has not violated the laws, regulations and rules.


(8) there are no major quality accidents caused by the supervision responsibility of the enterprise within two years prior to the date of applying for the qualification of project supervision.


(9) in the two years prior to the date of applying for the qualification of project supervision, there were no major safety accidents of project construction at or above the third level or two or more than two safety accidents of the project construction of the fourth grade due to the supervision responsibility of the enterprise.


2. Class B.


(1) having the status of an independent legal person and having a registered capital of not less than 1 million yuan.


(2) the technical person in charge of the enterprise shall be a registered supervision engineer with more than 10 years of experience in engineering construction.


(3) the total number of registered supervisory engineers, registered cost engineers, first-class registered architects, first-class registered structural engineers or other survey and design registered engineers shall not be less than 15. Among them, the corresponding professional registered supervision engineer is not less than the number required in the Professional qualification registered Supervision engineer equipment Table (schedule 1), and the registered cost engineer is not less than one.


(4) it has a relatively perfect organizational structure and quality management system, as well as technical and archival management systems.


(5) necessary engineering test and testing equipment.


(6) within two years prior to the date of applying for the qualification of project supervision, the enterprise has not violated the laws, regulations and rules.


(7) there are no major quality accidents caused by the supervision responsibility of the enterprise within two years prior to the date of applying for the qualification of project supervision.


(8) within two years prior to the date of applying for the qualification of project supervision, there were no major safety accidents in the construction of projects at or above the third level or two or more than two accidents in the construction of projects at or above the fourth level due to the supervision responsibility of the enterprise.


3. Class C


(1) having the status of an independent legal person and having a registered capital of not less than 500000 yuan.


(2) the technical person in charge of the enterprise shall be a registered supervision engineer with more than 8 years of experience in engineering construction.


(3) the number of registered supervision engineers in the corresponding profession shall not be less than the number required in the Professional qualification registered Supervision engineer equipment Table (schedule 1).


(4) have necessary quality management system, file management and rules and regulations.


(5) necessary engineering test and testing equipment.


(3) qualification standards of firms


1. Obtain the business license of the partnership and have a written cooperation agreement.


2. Among the partners, there are not less than 3 registered supervision engineers, all of whom have more than 5 years working experience in construction project supervision.


3. There is a fixed workplace.


4. Necessary quality management system, file management and rules and regulations.


5. Necessary engineering test and testing equipment.


II. Scope of business


(1) Comprehensive qualifications


Can undertake all professional engineering types of construction project supervision business, as well as construction project management, technical consulting and other related services.


(2) Professional Class A qualification


Can undertake the corresponding professional engineering category of construction project supervision business (see schedule 2), as well as the corresponding category of construction project management, technical consulting and other related services.


(3) Professional Class B qualification


It can undertake the engineering supervision business of the construction projects below the corresponding professional engineering category II (including Grade II) (see schedule 2), as well as the project management, technical consultation and other related services of the corresponding category and level construction projects.


(4) Professional Grade C qualification


It can undertake the engineering supervision business of the third-level construction project of the corresponding professional engineering category (see schedule 2), as well as the project management, technical consultation and other related services of the corresponding category and level construction project.


(5) qualification of the firm


Can undertake the engineering supervision business of the third-level construction project (see schedule 2), as well as the corresponding category and level of construction project management, technical consulting and other related services. With the exception of the construction project supervision business where compulsory supervision must be carried out according to the provisions of the state.


 20210408215718651865

Schedule 2

Professional engineering category and rating table

 

Serial number
Engineering category
First level
Second level
Three levels
oneHouse
Architecture
Engineering
General public buildingsMore than 28 stories; more than 36 meters span (except light steel structure); single project construction area of more than 30,000 square meters14Mui 28 storeys; 24Mel 36m span (except light steel structure); single project construction area of 10,000-30,000 square metersLess than 14 stories; less than 24 meters span (except light steel structure); single project construction area less than 10,000 square meters
Towering construction projectHeight more than 120 metersThe height is 70m / 120mHeight below 70m
Housing projectThe construction area of the residential area is more than 120000 square meters, and the individual project has more than 28 floors.Construction area of 60, 000-120000 square meters; 14, 000-28 floors of individual projectsThe construction area is less than 60,000 square meters and the individual project is less than 14 floors.
twoSmelting
Engineering
Iron and steel smelting and continuous casting projectAnnual output of more than 1 million tons; single blast furnace capacity of more than 1250 cubic meters; single nominal capacity converter more than 100 tons; electric furnace more than 50 tons; annual output of continuous casting more than 1 million tons or more than 1450 mm of single slab continuous casting machineAnnual output less than 1 million tons; single blast furnace capacity less than 1250 cubic meters; single nominal capacity converter less than 100 tons; electric furnace less than 50 tons; annual output of continuous casting less than 1 million tons or slab continuous casting machine less than 1450 mm
Steel rolling engineeringThe annual output of hot rolling is more than 1 million tons, equipped with continuous and semi-continuous rolling mills, cold-rolled strip and plate with an annual output of more than 1 million tons, cold-rolled wire rod with an annual output of more than 300000 tons, or equipped with continuous and semi-continuous mills.Hot rolling with an annual output of less than 1 million tons, equipped with continuous and semi-continuous mills, cold rolled strip with an annual output of less than 1 million tons, cold rolled wire rod with an annual output of less than 300000 tons, or equipped with continuous and semi-continuous mills
Smelting auxiliary engineeringThe annual output of coking project is more than 500000 tons or the height of carbonization chamber is more than 4.3m, single sintering machine is more than 100m2, and oxygen production per hour is more than 300m3.The annual output of coking project is less than 500000 tons or the height of carbonization chamber is less than 4.3m; a single sintering machine is less than 100m2: less than 300m3 of oxygen per hour
Non-ferrous smelting projectThe annual output of non-ferrous smelting is more than 100000 tons, that of non-ferrous metal processing is more than 50, 000 tons, and that of alumina project is more than 400000 tons.The annual output of non-ferrous smelting is less than 100000 tons, that of non-ferrous metal processing is less than 50, 000 tons, and that of alumina project is less than 400000 tons.
Building materials engineeringDaily output of cement is more than 2000 tons; daily melting capacity of floating glass is more than 400 tons; pool kiln wiredrawing glass fiber and special fiber; special ceramic production line projectCement daily output less than 2000 tons: floating glass daily melting capacity less than 400t; ordinary glass production line; combined furnace wiredrawing glass fiber; non-metallic materials, fiberglass, refractories, construction and sanitary ceramics factory engineering
threeMine
Engineering
Coal mine engineeringA mine project with an annual output of more than 1.2 million tons; a coal washing project with an annual output of more than 1.2 million tons; a vertical shaft project with a depth of more than 800m; an open-pit mine project with an annual output of more than 4 million tonsMine works with an annual output of less than 1.2 million tons; coal washing projects with an annual output of less than 1.2 million tons; vertical shaft projects with a depth of less than 800m: open-pit mine projects with an annual output of less than 4 million tons
Metallurgical mine engineeringBlack mine mining and separation projects with an annual output of more than 1 million tons; non-ferrous placer mining and separation projects with an annual output of more than 1 million tons; and non-ferrous vein mining and separation projects with an annual output of more than 600000 tonsThe mining and separation project of black mine with an annual output of less than 1 million tons; the mining and separation project of non-ferrous placer with an annual output of less than 1 million tons; and the mining and separation project of non-ferrous vein ore with an annual output of less than 600000 tons
Chemical mine engineeringPhosphate rock and pyrite project with an annual output of more than 600000 tonsPhosphate rock and pyrite projects with an annual output of less than 600000 tons
Uranium mine engineeringUranium ore with an annual output of more than 100000 tons; uranium processing and smelting with an annual output of more than 200tUranium ore with an annual output of less than 100000 tons; uranium processing and smelting with an annual output of less than 200t
Non-metallic mineral engineering of building materialsLimestone ore with an annual output of more than 700000 tons; gypsum ore and quartz sandstone ore with an annual output of more than 300000 tonsLimestone ore with an annual output of less than 700000 tons; gypsum ore and quartz sandstone ore with an annual output of less than 300000 tons
fourChemical engineering
Petroleum
Engineering
Oil field engineeringCrude oil processing capacity of more than 1.5 million tons per year, natural gas processing capacity of more than 1.5 million square meters per day, production capacity of more than 500000 tons and supporting facilitiesCrude oil processing capacity less than 1.5 million tons per year, natural gas processing capacity less than 1.5 million tons per day, production capacity less than 500000 tons and supporting facilities
Oil and gas storage and transportation engineeringPressure vessels above 8MPa; oil and gas storage tanks above 100000 cubic meters per unit; long-distance pipelines above 120kmPressure vessels below 8MPa; oil and gas storage tanks below 100000 cubic meters per unit; long-distance pipelines below 120km
Oil refining and chemical engineeringPrimary processing and corresponding secondary processing and post-processing equipment with crude oil processing capacity of more than 5 million tons per yearPrimary processing and corresponding secondary processing and post-processing units with a crude oil processing capacity of less than 5 million tons per year
Basic raw material engineeringEthylene projects with an annual output of more than 300000 tons; synthetic rubber, synthetic resins, plastics and chemical fiber projects with an annual output of more than 40, 000 tonsEthylene projects with an annual output of less than 300000 tons; synthetic rubber, synthetic resins, plastics and chemical fiber projects with an annual output of less than 40, 000 tons
Chemical fertilizer projectAnnual output of more than 200000 tons of synthetic ammonia and corresponding post-processing equipment; annual output of more than 240000 tons of ammonia phosphate projectAnnual output of less than 200000 tons of synthetic ammonia and corresponding post-processing equipment; annual output of less than 240000 tons of ammonia phosphate project
Acid-base engineeringThe annual output of sulfuric acid, caustic soda and soda ash is more than 160000 tons, 80, 000 tons and 400000 tons respectively.The annual output of sulfuric acid is less than 160000 tons, caustic soda less than 80, 000 tons and soda ash less than 400000 tons
Tire engineeringAnnual output of more than 300000 setsAnnual output of less than 300000 sets
Nuclear chemical and processing engineeringA uranium conversion chemical project with an annual output of more than 1000 tons; a uranium enrichment project with an annual output of more than 100 tons; a spent fuel reprocessing project with a total investment of more than 1 billion yuan; a fuel element processing project with an annual output of more than 200 tons; a nuclear technology and isotope application project with a total investment of more than 50 million yuanA uranium conversion chemical project with an annual output of less than 1000 tons; a uranium enrichment project with an annual output of less than 100 tons; a spent fuel reprocessing project with a total investment of less than 1 billion yuan; a fuel element processing project with an annual output of less than 200 tons; nuclear technology and isotope application projects with a total investment of less than 50 million yuan
Pharmaceutical and other chemical engineeringThe total investment is over 100 million yuanTotal investment of less than 100 million yuan
fiveWater conservancy
Water and electricity
Engineering
Reservoir engineeringTotal storage capacity of more than 100 million cubic meters

Total storage capacity of 10 million to 100 million cubic meters

Total storage capacity below 10 million cubic meters
Hydraulic power station projectTotal installed capacity above 300MWTotal installed capacity 50MW-300MWTotal installed capacity below 50MW
Other water conservancy projectsDiversion dike grade 1; irrigation and drainage flow more than 5 cubic meters per second; river regulation area more than 300000 mu; urban flood control urban population more than 500000; reclamation area more than 50, 000 mu; comprehensive control area of soil and water conservation more than 1000 square kilometersGrade 2 and 3 of water diversion dike; irrigation and drainage discharge 0.55m3 / s; river regulation area 30000-300000 mu; urban flood control urban population 200000-500000; reclamation area 5000-50000 mu; comprehensive control area of soil and water conservation 100,1000 square kilometersGrade 4 and 5 of diversion dikes; irrigation and drainage discharge less than 0.5 cubic meters per second; river regulation area less than 30, 000 mu; urban flood control urban population less than 200000; reclamation area less than 5000 mu; comprehensive control area of soil and water conservation less than 100 square kilometers
sixpower
Engineering
Thermal power station projectSingle machine capacity of more than 300000 kilowattsThe unit capacity is less than 300000 kilowatts
Power transmission and transformation projectMore than 330 kVBelow 330 kV
Nuclear power engineeringNuclear power plant; nuclear reactor engineering.

sevenAgriculture and forestry
Engineering
General Project of Forestry Bureau (Farm)The area is more than 350000 hectares.An area of less than 350000 hectares
Forest products industrial engineeringThe total investment is over 50 million yuanThe total investment is below 50 million yuan
Comprehensive agricultural development projectThe total investment is over 30 million yuanThe total investment is below 30 million yuan
Planting engineeringMore than 20 million mu or a total investment of more than 15 million yuanLess than 20, 000 mu or total investment less than 15 million yuan
Veterinary / animal husbandry engineeringThe total investment is over 15 million yuanThe total investment is below 15 million yuan
Fishery engineeringThe total investment of fishing port project is more than 30 million yuan, and that of other projects such as aquaculture is more than 15 million yuan.The total investment of fishing port project is less than 30 million yuan, and that of other projects such as aquaculture is less than 15 million yuan.
Facility agricultural engineeringThe facility horticulture project is more than 1 hectare, and the total investment of other projects such as agricultural products processing is more than 15 million yuan.The facility horticulture project is less than 1 hectare, and the total investment of agricultural products processing and other projects is less than 15 million yuan.
Decommissioning of nuclear facilities and disposal of radioactive wastesThe total investment is over 50 million yuanThe total investment is below 50 million yuan
eightRailroad
Engineering
Comprehensive railway engineeringNew construction or reconstruction of first-class trunk lines; more than 40 km of single-track railway; more than 30 km of double-track lines and hubsSingle-track railway less than 40 km; double-track less than 30 km; secondary trunk lines and station lines; special lines and special railways
Railway bridge engineeringThe bridge is more than 500 meters longThe bridge is less than 500 meters long
Railway tunnel engineeringMore than 3000 meters for single line and more than 1500 meters for double linesBelow 3000 meters for single line and less than 1500 meters for double lines
Railway communication, signal and electric power electrification engineeringNew construction or reconstruction of railways (including hubs, distribution, substations and district kiosks) with odd and double lines of 200 km and aboveNew construction or reconstruction of railways (excluding hubs, distribution, substations and district kiosks) with odd and double lines up to 200 km
nineHighway
Engineering
Highway engineeringExpresswayHighway subgrade engineering and first-class highwayThe roadbed engineering of the first-class highway and the highway below the second class
Highway bridge engineeringIndependent bridge project; the total length of the bridge is more than 1000 meters or the single span is more than 150mThe total length of the bridge and the middle bridge is 30m / 1000m or the single span is 20m / 150m.The total length of the bridge is less than 30 meters or the single span is less than 20 meters; culvert works
Highway tunnel engineeringThe length of the tunnel is over 1000 metersThe length of the tunnel is 500,000m.The tunnel length is less than 500 meters.
Other projectsCommunication, monitoring, toll collection and other mechanical and electrical projects, highway traffic safety facilities, environmental protection projects and ancillary facilities along the routeFirst-class highway traffic safety facilities, environmental protection projects and ancillary facilities along the routeSecondary and below highway traffic safety facilities, environmental protection works and ancillary facilities along the route
tenPort and waterway engineeringPort engineeringContainer, miscellaneous, multi-purpose and other coastal port projects above 20000 tons; bulk cargo and crude oil coastal port projects above 30000 tons; inland river port projects above 1000 tonsContainer, miscellaneous, multi-purpose and other coastal port projects below 20000 tons; bulk cargo and crude oil coastal port projects below 30000 tons; inland river port projects below 1000 tons
Navigable building and renovation projectMore than 1000 tonsBelow 1000 tons
Waterway engineeringComplex coastal waterways for ships of more than 30000 tons; inland navigation projects for ships of more than 1000 tonsCoastal waterways for ships of less than 30000 tons; inland navigation projects for ships under 1000 tons
Hydraulic engineering for repairing and building shipsDock works with a capacity of more than 10000 tons; berths and slipways with a hull weight of more than 5000 tonsDock works under 10000 tons; berths and slipways with hull weights below 5000 tons
Breakwater, diversion breakwater and other hydraulic projectsThe maximum water depth is more than 6 meters.The maximum water depth is less than 6 meters
Other waterway engineering projectsCoastal waterway projects with a construction cost of more than 60 million yuan; inland waterway projects with a construction cost of more than 40 million yuanCoastal waterway projects with a construction cost of less than 60 million yuan; inland waterway projects with a construction cost of less than 40 million yuan
elevenAerospace engineeringCivil airport engineeringThe index of the flight area is 4e or above and its supporting projectsThe index of the flight area is 4D or less and its supporting projects
Aerial vehicleThe total investment of aviation aircraft (integrated) project is more than 100 million yuan, and the total investment of aviation aircraft (individual) project is more than 30 million yuan.The total investment of aviation aircraft (integrated) project is less than 100 million yuan, and the total investment of aviation aircraft (individual) project is less than 30 million yuan.
Space vehicleThe total investment of the project is more than 30 million yuan; the area is more than 3000 square meters; the span is more than 18 meters.The total investment of the project is less than 30 million yuan, the area is less than 3000 square meters, and the span is less than 18 meters.
twelveCommunication engineeringWired and wireless transmission and communication engineering, satellite, integrated wiringInter-provincial communication and information network engineeringCommunication and information network engineering in the province
Postal, telecommunications, broadcasting hub and exchange projectsPostal and telecommunications hubs in provincial capital citiesPostal and telecommunications hubs in prefectural and municipal cities
Launch pad engineeringTotal transmission power more than 500 kilowatts of short wave or more than 600 kilowatts of medium wave transmission stations; radio and television transmission towers over 200 meters in heightTotal transmission power less than 500 kilowatts short wave or less than 600 kilowatts medium wave transmission station; radio and television transmission tower below 200 meters in height
thirteenMunicipal public worksUrban road engineeringUrban expressways, trunk roads, urban interchanges and bridges with a single hole span of more than 100m; tunnels with a length of more than 1000 mUrban secondary trunk road projects, urban separated overpasses and bridges with a single-hole span of less than 100m; tunnels less than 1000 m in lengthUrban slip road works, street flyovers and underground passage projects.
Water supply and drainage engineeringWater supply plants over 100000 tons per day; sewage treatment projects over 50, 000 tons per day; water supply and sewage pumping stations over 3 cubic meters per second; rain pumping stations over 15 cubic meters per second; water supply and drainage pipes over 2.5 meters in diameter20-100000 t / d water supply plant; 10-50 t / d sewage treatment works; 1Mel 3m3 / s water supply and sewage pumping station; 5Mel 15m3 / s rain pumping station; 1Mel 2.5m in diameter water supply pipeline; 1.5mi 2.5m in diameter drainage pipeWater supply plants below 20,000 tons per day; sewage treatment works under 10,000 tons per day; water supply and sewage pumping stations below 1 cubic meter per second; rain pumping stations below 5 cubic meters per second; water supply pipes with diameters less than 1 meter; drainage pipes less than 1.5 meters in diameter
Gas thermal engineeringLPG storage yard (station) with a total storage capacity of more than 1000 cubic meters; gas projects with a gas supply scale of more than 150000 cubic meters per day; gas pipelines and pressure regulating stations above medium pressure; thermal projects with a heating area of more than 1.5 million square metersLPG storage yard (station) with a total storage capacity of less than 1000 cubic meters; gas projects with a gas supply scale of less than 150000 cubic meters per day; gas pipelines and pressure regulating stations below medium pressure; thermal projects with a heating area of 500000-1.5 million square metersThermal projects with heating area less than 500000 square meters
Garbage disposal projectWaste incineration and landfill projects of more than 1200 tons per day.Municipal solid waste incineration and landfill projects of 500,000,000 tons per dayWaste incineration and landfill projects of less than 500 tons per day
Subway light rail projectAll kinds of subway light rail projects.

Landscape architecture engineeringThe total investment is over 30 million yuanThe total investment is 10 million-30 million yuanThe total investment is below 10 million yuan
fourteenMechanical and electrical installation engineeringMechanical engineeringThe total investment is over 50 million yuanTotal investment less than 50 million
Electronic engineeringThe total investment is more than 100 million yuan; projects with purification level 6 or aboveThe total investment is less than 100 million yuan; projects with purification levels below level 6
Textile engineeringThe total investment is over 50 million yuanThe total investment is below 50 million yuan
Weapon engineeringConstruction and installation projects costing more than 30 million yuan for tanks, armored vehicles, explosives, projectiles, guns and optoelectronics projects costing more than 20 million yuan, and chemical and civil explosion prevention projects costing more than 10 million yuan.Construction works cost less than 30 million yuan for tanks, armored vehicles, explosives, projectiles, guns and optoelectronics projects with construction costs less than 20 million yuan, and chemical and civil explosion prevention projects with construction costs less than 10 million yuan.
Ship engineeringThe total investment in shipbuilding engineering is more than 100 million yuan, and the total investment in ship scientific research, machinery and repair projects is more than 50 million yuan.The total investment of shipbuilding engineering is less than 100 million yuan, and that of ship scientific research, machinery and repair engineering is less than 50 million yuan.
Other projectsThe total investment is over 50 million yuanThe total investment is below 50 million yuan

Description

1. "above" in the table contains the number of books, and "below" does not include the number of books.

2. Other professional projects not listed in this table shall be graded by the relevant departments of the State Council in the corresponding categories of projects in accordance with the relevant provisions.

3. Housing construction projects include civil air defense projects that combine urban construction with civil construction.